| School | Project | %/Complete | Completion | | Valley Forge | Pool Paint | 100% | November 1, 2005 | | John Muir | Chimney | 100% | December 28, 2005 | | PSH | Little Theatre Rigging-lights-AC | 100% | May 16, 2006 | | John Muir | Chimney Phase 2 | 100% | April 21, 2006 | | Parma Park | Drainage | 100% | July 15, 2006 | | Normandy | Drainage | 100% | July 15, 2006 | | State Road | Interior Reno. | 100% | August 1, 2006 | | PSH | Steel Package | 100% | August 1, 2006 | | PSH | Locker Rooms/ Restrooms 100% | August 1, 2006 | | | HS (ALL) | Bleachers | 100% | August 1, 2206 | | PSH | Biology Area | 100% | August 15, 2006 | | System Wide | Fire Alarm up-grade | 95% | August 15, 2006 | | District | Roofing | 99% | August 15, 2006 | | PSH | Pool (revised) | 10% | November 1, 2006 | | Dentzler | Flooring | 100% | August 15, 2006 | | Dage | Flooring | 100% | August 15, 2006 | | Ridge-Brook | Flooring | 100% | August 15, 2006 | | PSH | Administration Relo | 100% | July 1, 2007 | | PSH | Classroom relo. | 100% | August 25, 2006 | | PSH | ACM Abatement | 100% | June 16, 2006 | | Valley Forge | Maint. Relocation | 70% | September 15, 2006 | | Valley Forge | Student Area | 100% | August 18,2006 | | Dentzler | Back Stairs | 100% | August 15, 2006 | | Hanna | Gas House | 100% | August 15, 2006 | | Parma Park | Step Replacement | 100% | August 15, 2006 | | Shiloh | Loading Dock | 100% | August 15, 2006 | | Shiloh | Step Repair (west) | 100% | August 15, 2006 | | John Muir | Tuck Point | 100% | August 15, 2006 | | PSH | Boilers | 10% | October 1, 2006 | | Byers | WEST Steel Repair | 80% | August 11, 2006 | | Normandy | Gym Ceiling | 75% | August 15, 2006 | | PSH | Gym Ceiling | 60% | August 15, 2006 | | Pleasant V. | Classroom | TBD | January 1, 2007 | | Normandy | Gym Floor | 20% | September 30, 2006 | | Valley Forge | Gym Floor | Bid 8/2 | September 30,2006 |
|
|